The Project

Located on Portland Street, this ‘Brooklyn’ theme hotel features 189 luxury bedrooms, complete with ground floor restaurant, bar & 9th floor function suite. The hotel also features the UKs first fully accessible ‘Liberty’ suite.

The Facts:

Client - Brooklyn Hotels – Bespoke Hotels
Main Contractor - Marshall Construction
Location - Portland Street, Manchester
Contract period - September 2018 - January 2020

The Work

A F Connell Ltd undertook the design, installation, testing and commissioning of all the mechanical, electrical and plumbing services. We were fully integrated into the design team from the concept & planning stage of the project to the commissioning of a fully functional facility for Bespoke Hotels and Marshall Construction. The services installed include ventilation, heating, domestic hot and cold water systems, full electrical distribution systems including metering and associated switchgear, all lighting and controls, power, integrated audio & visual systems, security, CCTV, access control, data systems, fire alarm. life safety systems etc.